Most full bathroom remodels in the Chicago suburbs take 2 to 4 weeks of work in your house. A refresh or powder room takes 1 to 2 weeks, a tiled tub-to-shower conversion 5 to 10 working days, and a primary or custom bathroom 4 to 8 weeks. If plumbing or electrical changes, your village reviews the permit first, which typically adds 1 to 3 weeks before anyone starts. The other wait people don't expect: frameless glass is measured after the tile is done and takes 10 to 14 days to make. So if Thanksgiving is the goal, a refresh can make it. A full remodel started in late October usually won't.
A bathroom is the smallest room we remodel and the one people expect to be quickest. On site, it usually is. What stretches the calendar is everything around the work: picking the vanity and tile, the permit review, and the glass. We covered the money side in our Frankfort bathroom cost guide and the Orland Park tub-to-shower guide. This one is about time, with the ranges we see on most bathrooms in Orland Park, Tinley Park, Frankfort, and the south suburbs.
These are typical ranges, not promises. A 1978 hall bath with the original cast-iron tub behaves differently from a 2006 primary suite, and your actual schedule gets written down after I've seen the room.
How long does each type of bathroom remodel take?
Bathrooms sort into a few groups, and each one has a different thing setting the pace. Prices are our 2026 ranges for the Orland Park area.
| Bathroom project | Typical price | Weeks on site | Permit? | What sets the pace |
|---|---|---|---|---|
| Refresh (layout stays) | $8K to $15K | 1 to 2 weeks | Usually not | Vanity and top availability, your decisions |
| Mid-range remodel (most common) | $15K to $30K | 2 to 4 weeks | Yes, 1 to 3 week review first | Waterproofing, tile, inspections, glass |
| Primary or custom | $30K to $60K+ | 4 to 8 weeks | Yes | Layout changes, specialty tile, steam, frameless glass |
| Tub-to-shower conversion | Most $12K to $28K | 5 to 10 working days (acrylic 3 to 5) | Yes, when plumbing changes | Tile and glass fabrication |
| Powder room | Varies with scope | 1 to 2 weeks | Depends on scope | Vanity and fixture selection |
In the west suburbs the prices run a little higher (our Naperville bathroom guide has those tiers), but the weeks on site are about the same.
Where do the weeks go in a bathroom remodel?
This is the order every bathroom we remodel follows. It assumes a mid-range remodel with a new tiled shower and the toilet and vanity staying roughly where they are.
Before anyone swings a hammer
- Walkthrough and proposal (week 1). I look at the room, the plumbing from below if there's a basement, the exhaust fan, and the electrical panel. Most of the time I can get to your house the same week you call. The itemized proposal follows with a written timeline.
- Selections (depends mostly on you). Vanity, top, toilet, tile, shower valve and trim, glass style, lighting, and fan. This is the phase that runs long when nobody expects it to, because the tile can't be ordered until the vanity and shower layout are settled. In-stock choices keep it short; a special-order vanity or tile adds lead time.
- Permit (1 to 3 weeks, alongside ordering). If plumbing or electrical changes, we submit to your village as soon as the layout is final. Orland Park and Frankfort typically review in 1 to 2 weeks; Naperville and busier offices run 1 to 3. Materials get ordered during the review, and work doesn't start until they're in hand.
In your house (usually 2 to 4 weeks)
- Demo and rough-in (first few days on site). Old tile, tub, vanity, and toilet come out, and the work area gets sealed off. Then the plumber and electrician move the drain, valve, and circuits to where the new layout needs them. This is when we find out what's under the old tub.
- Rough inspection. The village inspects rough plumbing and electrical before anything gets covered. Each village schedules differently: Tinley Park does plumbing inspections in the morning window only, and Frankfort books requests received before 12:30 PM for the next business day.
- Backer board, waterproofing, and tile (the longest stretch). Cement board goes up behind the tub or shower, then the waterproofing membrane (Schluter Kerdi is our default; Wedi on steam showers and larger primary builds), then the pan, tile, and grout. Waterproofing is the step that can't be rushed, and it's the one that decides whether the shower is still dry in 20 years.
- Vanity, fixtures, and trim-out. Vanity and top set, toilet installed, shower valve trim and faucet connected, lights, mirror, fan, and GFCI outlets trimmed out, paint touched up.
- Glass (10 to 14 days after tile). Frameless glass is measured once the tile is done, then fabricated. The shower is usually usable before the door arrives. A semi-frameless or framed door moves faster.
- Final inspection and punch list. The village does its final inspection. We walk the room together with blue tape and mark anything that isn't right, like a caulk line or a door that needs adjusting. Punch items get fixed and the permit gets closed.
Some phases overlap. Paint and trim often happen while the glass is being made, which is how a mid-range bathroom lands at 2 to 4 weeks on site.
"In a bathroom, the waterproofing is the step you never see and the one that decides how the job turns out."
Do I need a permit for a bathroom remodel, and how long does it take?
A cosmetic refresh (new vanity on the same plumbing, new toilet, reglazed tub, new light and mirror) usually doesn't need one. Moving a drain, replacing a shower valve, adding circuits, or opening walls does. Unless you live in an unincorporated area, your village issues the permit, not the county. Cook County's Department of Building and Zoning handles unincorporated areas only.
Typical review times we see on bathroom work:
- Village of Orland Park: 1 to 2 weeks of plan review when plumbing or electrical changes, with fees typically $150 to $400.
- Village of Frankfort: $150 to $450 in fees and 1 to 2 weeks before work can start. Frankfort reviews applications through its online portal and posts its permit rules on the village Permits and Inspections page. Inspection requests received before 12:30 PM are scheduled for the next business day, per the village's contractor information page.
- City of Naperville: 1 to 3 weeks of plan review before demo.
- Village of Tinley Park: the village publishes a Bathroom Remodel Guide on its Building Permits page, and it lists exactly what the inspector will look for (more on that below).
The permit rarely decides your finish date, because the review runs while the vanity, tile, and fixtures are on order. What does cost time is an incomplete application or a failed inspection, which is why we submit complete drawings and build to the inspection list from day one.
What Tinley Park's inspectors look for
Tinley Park's guide is a good example of what a village expects in a remodeled bathroom. Among its requirements:
- Bathroom exhaust fans on timers, venting directly outdoors, with ducts insulated where they run through unconditioned space.
- Bathroom GFCI receptacles on their own 20-amp circuit.
- No tandem breakers in the panel. In an older panel that's already full, this can mean panel work before the new circuit goes in.
- Tile behind tubs and showers on cement board or an equivalent moisture-resistant backer. Existing green board has to come out.
- Interconnected smoke and carbon monoxide alarms installed when drywall is removed during the job.
- No hanging fixtures, pendants, or ceiling fans in the zone above the tub.
The village's inspection page also notes there are no plumbing inspections in the afternoon window, so a rough plumbing inspection has to land in the morning. None of this is unusual. It's the kind of detail that turns into a re-inspection and a lost few days when a crew isn't expecting it.
Why is there a wait for the glass shower door?
Frameless glass is cut to the finished opening, so the installer can't measure until the tile and grout are done. Fabrication typically takes 10 to 14 days after that. That's why a tiled shower often has a stretch between "tile done" and "door on." The shower is usually usable a couple of weeks before the door goes on.
Any quote that promises the glass "goes in the same week" is either using a stock framed door or setting up for gaps. A semi-frameless or framed door moves faster and costs less. Frameless looks better and is worth the wait for most primary bathrooms.
What slows a bathroom remodel down?
When a bathroom runs long, it's almost always one of these.
- What's under the old tub. Rotted subfloor, hidden water damage from a slow leak, or a corroded cast-iron stack. In the 1970s to 1990s homes across Orland Park and Tinley Park, finding at least one is normal. We price the likely fixes in the proposal so it isn't a surprise.
- Special-order materials. A vanity or tile that's on back order is the most common reason a start date moves. We don't schedule demo until materials are in hand.
- Inspections. A failed rough inspection means fixing the issue and rebooking, and the walls stay open until it passes. Inspector backlogs add days too.
- Electrical capacity. A full panel with no room for a new 20-amp bathroom circuit means panel work first.
- Change orders after tile is ordered. Changing the niche size, the shower layout, or the tile itself can restart a lead time. At ADG every change order is in writing with the price and the schedule impact before anything changes.
- Steam and curbless showers. A sealed, sloped ceiling and a recessed floor take extra days to get right. Curbless or steam builds typically add a week or two.
- Slow decisions. Every week spent choosing between two tiles is a week added to the front of the schedule.
Can I use my bathroom during the remodel?
Not the one being remodeled. Expect it to be out of service for the whole on-site stretch, from a week or two for a refresh to 4 to 8 weeks for a primary bathroom. We seal the work area with plastic, run HEPA filtration to limit dust, and shut off plumbing only to that room, so the rest of the house works normally.
If it's your only bathroom, tell me at the walkthrough. We phase the rough-in and finish work so you have working plumbing every night. The first few days (demo and rough-in) are the loud, dusty ones. Once the backer board is up, things get a lot quieter.
Your timeline is on paper before you sign.
Every ADG proposal has a written timeline next to the itemized scope, and behind every material line is the actual receipt or invoice. The timeline shows when selections need to be final, when the permit goes in, when materials are expected, when demo starts, and when the glass gets measured. If a supplier slips or an inspection gets rebooked, you hear about it with a new date.
Can a bathroom remodel be done before Thanksgiving?
Thanksgiving is November 26 this year, about four weeks out. Here's the honest math.
A refresh or powder room: usually yes. The work is 1 to 2 weeks and usually needs no permit. If the vanity, top, and fixtures you pick are in stock and you decide in the next week, guests get a new bathroom.
A tub-to-shower conversion: maybe. Permit review and materials take 1 to 2 weeks, then 5 to 10 working days on site. If everything moves at the short end, the shower can be usable by Thanksgiving, possibly with the glass door still on order.
A mid-range or primary remodel: probably not. A 1 to 3 week permit plus 2 to 8 weeks on site doesn't fit in four weeks, and I'd rather tell you that now than have a torn-out bathroom when family arrives. If your home has a second bathroom, a remodel that runs through the holidays is livable. If it doesn't, start after New Year's.
The holiday weeks themselves also run slow. Suppliers, fabricators, and village offices close or run thin around Thanksgiving and between Christmas and New Year's, so a project still going in late December tends to lose a few days.
The plan I'd actually recommend
Pick the vanity, tile, and glass style this fall while there's no deadline. Get the permit in and the materials ordered in December. Start demo in January, when crews and inspectors have more open days. You'll be using the new bathroom before spring, and you'll have made every decision without a holiday hanging over it.
Frequently Asked Questions
How long does a bathroom remodel take in the Chicago suburbs?
Most full bathroom remodels in the Chicago suburbs take 2 to 4 weeks on site. A refresh takes 1 to 2 weeks, a tub-to-shower conversion 5 to 10 working days, and a primary or custom bathroom 4 to 8 weeks. When plumbing or electrical changes, the village permit review typically adds 1 to 3 weeks before work starts.
How long does a small bathroom or powder room remodel take?
A powder room can usually be finished in 1 to 2 weeks on site. A refresh of a full hall bath that keeps the existing layout (new vanity, top, toilet, lighting, and tile floor, with the tub reglazed) also runs about 1 to 2 weeks and usually doesn't need a permit.
How long does a tub-to-shower conversion take?
Most tiled tub-to-shower conversions take 5 to 10 working days on site once materials are in hand. An acrylic or solid-surface conversion takes 3 to 5 days. Frameless glass is measured after the tile is done and takes 10 to 14 days to fabricate, and a curbless or steam build adds a week or two.
How long does a primary bathroom remodel take?
A down-to-the-studs primary bathroom typically takes 4 to 8 weeks on site. Steam showers, moving the toilet or shower, specialty tile, and frameless glass push it toward the long end. Plan review comes before that, and is usually 1 to 3 weeks depending on the village.
Do I need a permit for a bathroom remodel, and how long does it take?
A cosmetic refresh usually doesn't need one. Moving or replacing plumbing, adding circuits, or opening walls does, and in an incorporated suburb your village issues it. Orland Park and Frankfort typically review a bathroom permit in 1 to 2 weeks with fees of $150 to $450. Naperville runs 1 to 3 weeks.
Why is there a wait for the glass shower door?
Frameless glass can only be measured after the tile is finished, because the panels are cut to the exact finished opening. Fabrication typically takes 10 to 14 days after that. The shower is usually usable a couple of weeks before the door goes on, so plan for that gap rather than being surprised by it.
Can I use my bathroom during the remodel?
Not the one being remodeled. We seal the work area with plastic, run HEPA filtration to limit dust, and shut off plumbing only to that room. If it's your only bathroom, we phase rough-in and finish work so you have working plumbing every night.
What causes bathroom remodel delays?
The common ones: a special-order vanity or tile that arrives late, rotted subfloor or water damage found under an old tub, a corroded cast-iron stack, a failed rough inspection, an electrical panel with no room for the new circuits, change orders after tile is ordered, and the 10 to 14 day glass fabrication window.
Can a bathroom remodel be done before Thanksgiving?
Thanksgiving is November 26, 2026. If you're reading this in late October, a refresh or powder room with in-stock materials can realistically make it. A tub-to-shower conversion might, if the permit and materials move quickly, though the glass door may land after. A full or primary bathroom remodel started now usually won't.
What does Tinley Park require for a bathroom remodel permit?
The Village of Tinley Park's Bathroom Remodel Guide calls for exhaust fans on timers that vent outdoors, bathroom GFCI receptacles on their own 20-amp circuit, cement board behind tub and shower tile, no tandem breakers, and interconnected smoke and CO alarms when drywall comes off. Plumbing inspections are morning-only.
Want a real timeline for your bathroom?
Get a no-pressure walkthrough, an itemized quote, and a written schedule from a licensed Orland Park contractor. Pick your tile this fall, use your new bathroom by spring.