The Honest Answer

Most kitchen remodels in the Chicago suburbs take 3 to 5 months from the first phone call to the final inspection, and only 4 to 7 weeks of that is actual work in your house. A refresh (painted or refaced cabinets, new counters, new backsplash) runs about 5 to 10 weeks start to finish. A full custom kitchen with custom cabinets or a wall coming out runs 5 to 8 months. What surprises people is everything before demo: design, selections, a 1 to 3 week village permit, and cabinet lead times of 4 to 14 weeks. So if you're reading this in late September hoping to host Thanksgiving in a new kitchen, a refresh might make it. A full remodel almost certainly won't, and I'd rather tell you that now than in November.

Every fall somebody looks at their 1994 oak cabinets and decides this is the year. The first question is "how much," which we covered in our Orland Park kitchen cost guide. The second one, the one that matters in September, is "how long." Here's the straight answer, with the week ranges we see on most of our kitchens in Orland Park, Tinley Park, and the south suburbs.

These are typical ranges, not promises. A 1972 split-level behaves differently from a 2004 two-story, and your actual schedule gets written down after I've seen the room.

The quick answer: timelines by type of kitchen

Kitchens sort into three groups, and each one has a different thing setting the pace. Prices are our 2026 ranges for the Orland Park area.

Kitchen typeTypical priceStart to finishWeeks on siteWhat sets the pace
Refresh$15K to $30K5 to 10 weeks2 to 4 weeksCountertop fabrication, your decisions
Mid-range remodel (most common)$30K to $55K3 to 5 months4 to 7 weeksSemi-custom cabinet lead time
Full custom$55K to $80K+5 to 8 months7 to 10 weeksCustom cabinets, engineering if a wall moves

Notice the gap between the last two columns. On a mid-range kitchen, more than half the calendar goes by before anybody touches your house. That's normal.

Phase by phase: where the weeks actually go

This is the order every kitchen we remodel follows. The ranges are typical for a mid-range remodel with semi-custom cabinets and no wall coming out.

Before anyone swings a hammer (usually 6 to 12 weeks)

  1. Walkthrough and measure (week 1). I measure the room, look at the electrical panel, and check the pipes from the basement if there is one. Most of the time I can get to your house the same week you call. The itemized proposal follows with a written timeline.
  2. Design and selections (2 to 4 weeks). Layout, cabinets, countertop, sink, appliances, backsplash, flooring, lighting. Homeowners underestimate this phase most, because every decision waits on another one. Appliances get picked first, since the cabinets are sized around them down to the inch. A full custom kitchen usually takes 4 to 8 weeks here.
  3. Permits (1 to 3 weeks, alongside ordering). Most south Cook County villages issue a kitchen permit in 1 to 3 weeks after a complete application. We submit it as soon as the layout is locked, so the review happens while the cabinets are being made.
  4. Ordering and lead times (4 to 8 weeks for semi-custom cabinets). Typical 2026 cabinet lead times: stock 1 to 3 weeks, semi-custom (KraftMaid, Medallion, Wellborn) 4 to 8 weeks, full custom 8 to 14 weeks. Special-order appliances can take 4 to 12. We don't schedule demo until the cabinets have a confirmed ship date. Tearing out a kitchen and then waiting a month for boxes is how a 5-week remodel turns into a 10-week one.

In your house (usually 4 to 7 weeks)

  1. Demo (1 to 2 days). Old cabinets, counters, and flooring come out, and the work area gets sealed with zip walls. The loudest two days of the project.
  2. Rough-in and inspections (1 to 1.5 weeks). Plumbing, electrical, gas, and the range hood duct move to where the new layout needs them. Then the village inspects the rough plumbing and rough electrical, and nothing gets covered until those pass. In older homes this is also when surprises show up.
  3. Drywall, patch, and flooring (about 1 week). Hang, tape, mud, sand, prime. Joint compound needs drying time between coats, and rushing it shows up later under your new paint. Flooring that runs under the cabinets goes in now.
  4. Cabinet install (2 to 5 days). Boxes set, leveled, and fastened, then doors, drawers, panels, and crown. Heavily detailed custom work can take a week or more.
  5. The countertop gap (1 to 2 weeks). Once the base cabinets are set and level, the fabricator templates, cuts the slab, and comes back to install. For quartz and granite that's typically 5 to 10 working days. This is the stretch where the kitchen looks almost done and you still can't use the sink.
  6. Backsplash, trim-out, and appliances (1 to 1.5 weeks). Sink and faucet hooked up, backsplash tile set and grouted, outlets and under-cabinet lights trimmed out, appliances set and connected, paint touched up.
  7. Final inspection and punch list (2 to 5 days). The village does its final inspection. You and I walk the kitchen with blue tape and mark anything that isn't right, like a door that needs adjusting or a paint touch-up. Punch items get fixed and the permit gets closed.

Some phases overlap (painting often happens during the countertop gap), which is how a mid-range kitchen lands at 4 to 7 weeks on site.

"The work in your house is the short part. The weeks before demo decide whether the project finishes on time."

Can I have my kitchen done by Thanksgiving or the holidays?

This is the question I get every fall, usually right about now. Thanksgiving is November 26 this year, roughly eight and a half weeks out. Here's the honest math.

A mid-range or full remodel starting from scratch: no. Walkthrough and proposal take a week. Design and selections take 2 to 4 weeks. Semi-custom cabinets take 4 to 8 weeks to arrive, and the permit runs during that wait. The on-site work takes another 4 to 7 weeks. Put the fastest version of every phase back to back and you get roughly 11 weeks, which lands in mid-December. That's the best case, and I'm not going to tell you otherwise to win the job.

A refresh: sometimes. If you're painting or refacing the cabinets you have and putting in new quartz, a new sink and faucet, and a tile backsplash, the work itself is 2 to 4 weeks. If you pick a countertop and backsplash in the next week or two, and both are in stock, Thanksgiving is realistic. If you're still deciding in mid-October, it gets tight fast.

Christmas and New Year's. A refresh started in October should be done well before Christmas. A mid-range remodel could finish before Christmas only if the design is final by early October and the cabinets ship at the short end of their lead time. It can happen. I wouldn't plan a family dinner around it.

The holiday weeks themselves also run slow. Cabinet plants, fabricators, supply houses, and village offices close or run thin around Thanksgiving and between Christmas and New Year's, so a project still going in late December tends to lose days it can't get back.

The plan I'd actually recommend

Use the fall to design. Host the holidays in the kitchen you have. Start demo after New Year's. Sign in October or November, finish selections before the holidays, and order cabinets so they land in January or February. The torn-up weeks happen when nobody is coming over anyway. The version I want you to avoid is a kitchen with no countertops on Thanksgiving morning and twelve people ringing the doorbell.

What slows a kitchen remodel down

When a kitchen runs long, it's almost always one of these.

Living without a kitchen for a few weeks

On a mid-range remodel, figure on 4 to 7 weeks without a working kitchen, and about 3 to 5 weeks without a kitchen sink, since the sink can't go back in until the countertop is installed. Most of our clients stay in the house the whole time.

On dust: we seal the work area with plastic sheeting and zip walls, cover the HVAC returns near the kitchen, and clean up at the end of every day. The first two weeks (demo and rough-in) are the loud, dusty ones. After drywall, things quiet down a lot.

How village permits fit into the timeline

Unless you live in an unincorporated area, your village issues the permit, not Cook County. Most south Cook County villages turn a kitchen permit around in 1 to 3 weeks once the application is complete. Orland Park and Tinley Park typically run 1 to 2 weeks for a kitchen without structural work. Removing a load-bearing wall needs a stamped drawing from an Illinois-licensed structural engineer and usually 3 to 4 weeks. Unincorporated Cook County, handled by the county's Department of Building and Zoning, is slower: plan on 3 to 6 weeks. Fees typically run $150 to $700.

The good news is that permit time almost never decides your finish date, because it runs while the cabinets are being built. We submit the day the layout is final, and on a well-run job the permit is issued before the cabinets land. After that come the inspections: rough plumbing and rough electrical before the walls close, framing if a wall changed, insulation if an exterior wall was opened, and a final. Our Cook County kitchen permit guide covers what triggers a permit and how each village handles it.

How ADG Does It Differently

Your timeline is on paper before you sign.

Every ADG proposal has a written timeline next to the itemized scope, and behind every material line is the actual receipt or invoice. The timeline shows when selections need to be final, when the permit goes in, when the cabinets are expected, and when demo starts. If a supplier slips or an inspection gets rebooked, you hear about it with a new date.

Why winter design and a spring remodel work so well

If you're not racing the holidays, here's the calendar I'd pick for most families in the Chicago suburbs:

  1. October to December: walkthrough, design, and selections. Take your time in the showrooms and make decisions without a deadline hanging over them.
  2. December to January: permit submitted and issued, cabinets ordered. The lead time runs while you're busy with the holidays.
  3. February to March: cabinets arrive, demo, rough-in, inspections.
  4. March to April: countertops, backsplash, final inspection. You're cooking in the new kitchen before graduation parties and summer cookouts.

Spring start dates fill first. Most people start thinking about a kitchen when the weather turns warm, so the homeowners who designed over the winter get the early spots on the calendar.

Winter barely touches a kitchen. It's interior work. Beyond keeping the driveway clear for deliveries, snow rarely moves the schedule.

You make better decisions without a deadline. A countertop picked in a rush to beat Thanksgiving is more likely to be one you second-guess in a year.

The point is to do the deciding before the tearing out.

Frequently Asked Questions

How long does a kitchen remodel take in the Chicago suburbs?

Most mid-range kitchen remodels in the Chicago suburbs take 3 to 5 months from the first call to the final inspection, with 4 to 7 weeks of actual work in the house. A refresh takes about 5 to 10 weeks total, and a full custom kitchen 5 to 8 months. Design, permits, and cabinet lead times account for most of the difference.

How long does a kitchen remodel take once demo starts?

Typically 2 to 4 weeks for a refresh, 4 to 7 weeks for a mid-range remodel with semi-custom cabinets, and 7 to 10 weeks for a full custom kitchen. The longest single wait on site is the 1 to 2 week gap between countertop template and install. Demo should not start until the cabinets have a confirmed ship date.

Can I get my kitchen remodeled before Thanksgiving?

If you are starting from scratch in late September, a full remodel usually can't be finished by Thanksgiving (November 26, 2026). Design, a 1 to 3 week permit, 4 to 8 weeks for semi-custom cabinets, and 4 to 7 weeks on site put the earliest realistic finish in mid-December. A refresh can make it if you pick in-stock materials in the next week or two, since the on-site work takes 2 to 4 weeks.

Can a kitchen remodel be finished before Christmas?

A refresh started in October is typically done before Christmas. A mid-range remodel finishes before Christmas only if the design is final by early October and the cabinets ship at the short end of their 4 to 8 week lead time. Possible, but not something to count on. The better plan is to design this fall and start demo after New Year's.

How long are kitchen cabinet lead times in 2026?

Typical 2026 lead times: stock cabinets 1 to 3 weeks, semi-custom lines like KraftMaid, Medallion, and Wellborn 4 to 8 weeks, and full custom cabinetry 8 to 14 weeks. A damaged box that has to be remade can add a few more weeks.

How long is the gap between countertop template and install?

For quartz and granite, typically 5 to 10 working days, or about 1 to 2 weeks. The fabricator can only template after the base cabinets are installed and level. Natural stone where you pick your own slab can take longer.

How long does a kitchen remodel permit take in Cook County suburbs?

Most south Cook County villages issue a kitchen permit in 1 to 3 weeks after a complete application, and Orland Park and Tinley Park typically take 1 to 2 weeks for work without structural changes. Removing a load-bearing wall requires stamped engineering and usually 3 to 4 weeks. Unincorporated Cook County runs 3 to 6 weeks.

How long will I be without a kitchen during a remodel?

On a mid-range remodel, expect 4 to 7 weeks without a working kitchen and about 3 to 5 weeks without a kitchen sink, because the sink goes back in only after the countertops are installed. Most homeowners stay in the house and set up a temporary kitchen near a utility sink.

What causes kitchen remodel delays?

The most common causes are change orders after cabinets are ordered, which can restart a cabinet's lead time; custom cabinets at 8 to 14 weeks; incomplete permit applications; failed rough inspections; back-ordered appliances at 4 to 12 weeks; and hidden conditions in older homes such as galvanized pipes.

When is the best time of year to start a kitchen remodel in the Chicago area?

For most families, design and permit in the fall and winter, then remodel in late winter or early spring. Selections October through December, cabinets ordered by January, and demo in February or March typically means a finished kitchen by April. Winter weather rarely affects interior kitchen work, and spring start dates fill first.